First job was to set the site up by creating a new access point onto Eastern Parade by installing new site gates and a drop curb. We then erected temporary fencing to secure the site and installed a haul road and crane pad from Eastern Parade up to the existing pavilion.
The existing pavilion was clad in asbestos which was very carefully removed and disposed of. Following this demolition happened very quickly.